Building Permit Drawings in Ontario: What Homeowners Need to Know (No Jargon)
A plain-language guide to permit drawings in Ontario: what they are, when you need them, which drawings make up a set, and what happens during municipal review.

Planning a renovation or an addition in Ontario? You will probably need building permit drawings before work starts. They show what you intend to build and how it meets the Ontario Building Code. The process looks daunting from the outside, but it is more predictable than it first appears.
What Are Building Permit Drawings?
Building permit drawings are the drawings and documents submitted with a building permit application, so your municipality can review the proposed work. They are not sketches. They are scaled, dimensioned drawings that show the work in enough detail for a plan examiner to check it against the Building Code and local bylaws.
Depending on the project, a set can include a site plan, floor plans, elevations, building sections, construction details and notes. Engineering, HVAC design and other specialist documents are separate where they are required.
Whether you are finishing a basement, adding a second storey or building a new house, the approved drawings become the reference for inspections during construction.
When Do You Need a Permit?
Most structural and substantial work needs a permit. Common examples include:
- New house construction
- Additions and extensions
- Finishing a basement, particularly where walls, plumbing or electrical change
- Structural changes such as removing a load-bearing wall
- Converting space, for example turning a garage into living space
- Creating a second unit
- Many decks, depending on their height above grade, size and whether they are attached to the house
Some smaller work does not need a permit. The thresholds are specific, and they differ between municipalities. Your municipal building department is the authority on whether your particular project needs a permit, and asking costs nothing.
It is worth asking. Work done without a required permit tends to surface during a sale, and resolving it then is considerably more expensive than doing it properly at the time. See retroactive building permits if that has already happened.
The Drawings in a Typical Set
Site plan
The site plan shows your property from above:
- Property boundaries and dimensions
- Existing buildings and structures
- Where the proposed work sits
- Setbacks from property lines
- Driveways, walkways and hard surfaces
- Grading and drainage, where relevant
Plan examiners use it to check setbacks and lot coverage against the zoning bylaw. Some municipalities require it to be based on a current survey. See technical drafting for how these are prepared.
Floor plans
Floor plans show the layout of each level:
- Room dimensions and names
- Door and window locations and sizes
- Fixtures and built-in elements
- Ceiling heights
- Stairs, with dimensions
For renovations you usually need to show both existing and proposed conditions, so the reviewer can see exactly what changes.
Elevations
Elevations show the exterior from each side:
- Overall heights and the relationship to grade
- Exterior materials and finishes
- Window and door openings
- Roof slopes and lines
They let the reviewer check height limits and how the building meets the ground.
Construction details and other documents
Depending on complexity you may also need foundation plans, framing plans, building sections, construction details, HVAC design and energy efficiency documentation.

Can You Prepare Your Own Drawings?
In limited circumstances, Ontario allows a person to prepare drawings for their own project without being a qualified and registered designer. The circumstances are specific and narrow.
Owning the property is not on its own the test. The exemption turns on the kind of building and the nature of the work, not simply on whose name is on the title, and it does not extend to every residential project. A building that falls outside Part 9, or one that requires design by an architect or a professional engineer, is not brought within the exemption by the fact that you own it. Ask your municipality whether it applies to the specific project you are planning, before you start drawing.
Whoever prepares them, the drawings must still meet the same technical requirements. The exemption changes who may draw them. It does not lower the standard they have to meet.
When doing it yourself may work
- Simple work with little or no structural change
- Straightforward projects using conventional construction
- Cases where you have relevant experience
- Cases where you have time to research the requirements properly
When it is worth hiring someone
Consider a BCIN-qualified designer, an architect or an engineer when:
- The work involves meaningful structural change
- You are working to the limits of a zoning bylaw
- The project is large or unusual
- You need the submission to be complete first time
- The value of the project justifies the fee
Municipal Review
Once the application is submitted, the municipality reviews it against the Ontario Building Code, the zoning bylaw, and other applicable requirements such as conservation authority approval where that applies.
How long it takes
Once an application is complete, the Building Code sets a period within which the chief building official must either issue the permit or refuse it in writing with all the reasons for the refusal. The periods are in Division C, Article 1.3.1.3 and its Table 1.3.1.3:
| Class of building | Period |
|---|---|
| A house where no dwelling unit is located above another, other than a retirement home, and a detached structure serving it not exceeding 55 m² in building area | 10 business days |
| Buildings described in Division A, Clause 1.3.3.3.(1)(a), (b) or (c), other than those in the rows above and below; farm buildings not exceeding 600 m² in building area | 15 business days |
| Buildings described in Division A, Sentence 1.3.3.2.(1), other than those in the first and last rows; farm buildings exceeding 600 m²; retirement homes | 20 business days |
| Post-disaster buildings, and buildings to which Subsection 3.2.6. of Division B or Articles 3.2.8.3. to 3.2.8.8. apply | 30 business days |
Four qualifications matter more than the numbers:
- These are business days. Sentence 1.3.1.3.(8) provides that the periods in Table 1.3.1.3 “shall not include Saturdays, holidays and all other days when the offices of the principal authority are not open for the transaction of business with the public”. Ten business days is around two calendar weeks, and longer across a holiday.
- The clock starts only when the application is complete, and the Code says what complete means: the prescribed form, an eligible applicant, every applicable field and required schedule completed and submitted, and the required fees paid. An incomplete submission does not start it. Under Sentence 1.3.1.3.(7) the period begins on the day following the day a complete application is submitted.
- The period is a deadline for a decision, not for an approval. A refusal issued in writing within the period satisfies it. Nobody can guarantee that a permit will be issued; the municipality reviews every application and makes that decision.
- Where one application covers buildings of different classes, the longer period applies.
Beyond that, elapsed time depends on municipal workload, the complexity of the project and how many rounds of revision are needed. The one thing within your control is submitting a complete, accurate application.
Handling review comments
If a plan examiner finds problems, you will get written comments setting out what needs to change. Common ones include:
- Missing dimensions or details
- Unclear construction methods
- Zoning conflicts such as setbacks or height
- Insufficient structural information
- Items that do not meet a Code requirement
Answer every comment fully and resubmit. Partial responses usually mean another review cycle.

What Makes a Good Set of Drawings
Accuracy. Dimensions, materials and details should reflect what will actually be built. Gaps become questions, and questions become delays.
Clarity. Standard symbols, sensible line weights and a logical sheet order help a reviewer find what they need.
Code compliance. The design has to meet the applicable requirements, and the drawings have to show that it does.
Consistency. Sheets that contradict each other are a common and avoidable cause of comments.
Before You Start
Talk to your municipality
Requirements vary. Ask your building department about local submission standards, the forms and documents required, fees, and anything specific to your area. See permit services for how we handle this.
Gather what you already have
Property surveys, previous permits and any existing drawings for the house all help. If none exist, measurements of the existing building will be needed. See as-built and existing conditions.
Settle the scope
Decide what you are building before drawings start. Changes made during review cost time and money.
Choosing Someone to Prepare Them
If you decide to hire, look for:
- Current registration, which you can check yourself in the QuARTS Public Search Registry
- Qualification categories that cover your type of building
- Experience in your municipality
- Comparable projects you can look at
- A clear written scope and fee, including how revisions are handled
At Neo-Scenic Designs we prepare building permit drawings for houses and small buildings in southwestern Ontario. We are a registered design firm, BCIN 206160. We are not architects or engineers, and where a project needs one we say so and coordinate with them.
In Short
Permit drawings are the foundation of the project. Getting them right is cheaper than fixing them later, whether you prepare them yourself or hire someone.
No one can guarantee an approval. The municipality reviews every application and makes the decision. What a good set of drawings does is remove the avoidable reasons for delay.
Ready to move forward? Contact our team to talk through your project.
Common questions
What are building permit drawings?
They are the drawings and documents submitted with a building permit application, so the municipality can review the proposed work. Depending on the project, they can include a site plan, floor plans, elevations, building sections, construction details and notes. What is needed depends on the project and the municipality. Engineering, HVAC design and other specialist documents are separate where required. See building permit drawings.
Does my renovation need a permit?
Not every renovation does. Changes to structure, plumbing, exits or how a space is used often do. Your building department decides; we can help you find out before you start.
Do I need a permit to finish my basement?
Often, yes, if the work adds rooms, changes plumbing, windows or exits, or creates a unit, but it depends on the work and your municipality. Your building department decides. Contact us and we can help you work out what applies before you start.
How long will my project take?
We discuss expected timelines during the initial assessment and in your written quotation. Actual timing depends on the project scope, the information required, any consultants involved and municipal review, so we do not promise a fixed turnaround.
How much do permit drawings cost?
It depends on the project: its size, what already exists on site, and which drawings and documents your municipality asks for. Starting prices for common projects are shown on our service pages, before HST. We confirm the scope and fees in a written quote before drawing work begins. If a site visit is needed to assess the project before quoting, it is billed separately. Where applicable, any credit for an initial site visit toward subsequent design services will be confirmed in your written quotation.
Are the images on this website photographs of finished projects?
Some are, and the drawings are from real drawing sets. Two other kinds of image are not photographs of our work, and they differ from each other. The architectural visualizations are AI-enhanced images produced from Neo-Scenic Designs project models: finishes, materials, landscaping, furnishings and some architectural details in them are generated or interpreted by software, so they show what a project could look like rather than approved or completed construction. The illustrations on our articles are AI-generated editorial images: they are not based on any Neo-Scenic Designs project, drawing, client or site, and they show generic scenes chosen to suit the article. The building permit drawings remain the authoritative design documents, and photorealistic rendering is not a standard part of our services.